ESM Checklist

Maharashtra Agricultural Competitiveness Project
Form ES1: Sub-project Screening at Pre-planning Stage
 
Name of Sub-Project:                                                                   
District:
Form to be filled by
Submitted to
When
Project Implementing Unit at field level (either APMC/RH or Implementing Line Dept – Officer in charge)
Project Co-ordination Unit (PCU) of MACP
Read more...
Maharashtra Agricultural Competitiveness Project
Form ES1: Sub-project Screening at Pre-planning Stage
 
Name of Sub-Project:                                                                   
District:
Form to be filled by
Submitted to
When
Project Implementing Unit at field level (either APMC/RH or Implementing Line Dept – Officer in charge)
Project Co-ordination Unit (PCU) of MACP
Along with the sub-project proposal
Sub-projects with any of the attributes listed below will be ineligible for support under the proposed project. Any project activity with the potential for significant conversion or degradation of critical natural habitats would be ineligible for support through the project. Including, but not limited to, any activity within:
  • Any project that is not consistent with applicable laws and regulations of the state.
  • Any project with the potential for significant damages to cultural property.
  • Any project that is not consistent with the project description at time of project negotiations, unless subsequently agreed to with the Bank along with the appropriate level of environmental and social management.
  • Any project or activity involving the procurement of pesticides not allowable under Bank guidelines 
Sr. No.
Question
Yes
No
1
Does the identified site fall under any Declared Forest Reserves or any Wildlife Reserves; National Parks and Sanctuaries
 
 
2
Does the site falls with in CRZ I or any CRZ zone where activities are not allowable in accordance with the CRZ Notification
 
 
3
Is the site less than 200 m from any natural water body, river, lake and natural wetland
 
 
4
Is the site less than 100 m from any dry river bed and man-made water body (except for aqua marts and fisheries activities)
 
 
5
Is the site located within any legally designated Protected Area (PA), such as National Park, Wildlife Sanctuary, Reserved Forest, Protect Forests etc
 
 
6
Is the use of site result in large-scale land use changes or habitat conversion
 
 
7
Will the project implementation at the site result in physical displacement of any person/family/household in selecting the site for implementing the project
 
 
 
Signature
:
 
Name of person filling form
:
 
Designation
:
 
For use of MACP
:
 
Signature
:
 
Name of person screening form at MACP
:
 
Designation
:
 
CRZ: Coastal Regulation Zone
Go top...