Institutional and Implementation Arrangements for Upgrading Livestock Yards

Institutional Arrangements:
MSAMB and Department of Cooperation is responsible for implementing the APMC modernization program for the Livestock markets. Technical help of PIU of Animal Husbandry Department would be taken by MSAMB. The role of PIU-MSAMB would be to liaise with the contractors and the service providers, approve variations and time extension, sample checking and joint verifications of the measurement books, process bills of the contractors and consultants and resolution of any disputes within the contracts.

MSAMB will be responsible for appointing Market Field Engineers on contract for qualit y control of the civil works. The specific tasks to be carried out by PIU (MSAMB), Dept of Cooperation, APMC and the service provider in the various stages of the project will be similar to those described under the para relating to Institutional Arrangements for the sub-component of Upgrading & Modernization of APMCs.

Implementation Arrangements of this sub-component would also be similar to the sub-component of Upgrading & Modernization of APMCs. The implementation of this sub-component would need SP who will be appointed.
Phasing of market modernization: The Livestock APMC modernization program would be taken on a phased manner as under:

Read more...
Institutional Arrangements:
MSAMB and Department of Cooperation is responsible for implementing the APMC modernization program for the Livestock markets. Technical help of PIU of Animal Husbandry Department would be taken by MSAMB. The role of PIU-MSAMB would be to liaise with the contractors and the service providers, approve variations and time extension, sample checking and joint verifications of the measurement books, process bills of the contractors and consultants and resolution of any disputes within the contracts.

MSAMB will be responsible for appointing Market Field Engineers on contract for qualit y control of the civil works. The specific tasks to be carried out by PIU (MSAMB), Dept of Cooperation, APMC and the service provider in the various stages of the project will be similar to those described under the para relating to Institutional Arrangements for the sub-component of Upgrading & Modernization of APMCs.

Implementation Arrangements of this sub-component would also be similar to the sub-component of Upgrading & Modernization of APMCs. The implementation of this sub-component would need SP who will be appointed.
Phasing of market modernization: The Livestock APMC modernization program would be taken on a phased manner as under:

 
Sr.No
 
APMC Markets
 
Yr-1
 
Yr-2
 
Yr-3
 
Yr-4
 
Yr-5
 
Yr-6
 
Total
APMC – Livestock Market Yard
1
Cattle Market
0
5
5
5
5
0
20
2
Small Ruminant Market
0
1
1
1
1
0
4
 
Total
0
6
6
6
6
0
24
 